Day 10 Construction

Day 10 Construction

Received inspection approval for in-ground plumbing, pouring concrete to seal the floor, starting to rough-in the duct work for the taproom HVAC.

Concrete finishing in the back of the house (eventually for additional employee restroom)

Concrete finishing for mop sink and back trench drain

Loading in concrete along back trench drain

Nervous concrete truck driver, wanting to get done with delivery to avoid setup in the truck

Roughing in HVAC ducting for the taproom